重庆彩电中心变电站原址带电整体改造

来源于: 发表时间:2011-12-02 15:12 编辑:fzy

温茂生(重庆广播电视集团(总台),重庆市 401147)

In-situ Reconstruction of the Whole Powered Transformer Substation
in Chongqing Television Center
 
Wen Maosheng(The Radio and Television Group of Chongqing,Chongqing 401147,China)
 
    Abstract This paper describes the entire process of in-situ reconstruction of the whole powered transformer substation within the limited space of transformer substation in Chongqing Television Center,including the transformation of project background,scheme selection,power supply mode of process loads,project contents,and construction procedures of the project.
    Key words Television center Transformer substation In-situ reconstruction of the whole powered transformer substation
 
    摘 要 介绍在重庆彩电中心变电站有限的空间范围内,原址带电整体改造,包括项目改造背景、方案选择、工艺负荷供电模式、改造内容和工程施工方法等。
    关键词 彩电中心 变电站 变电站原址带电整体改造
 