以原供电系统为扩建部分供电的可行性研究
吴华杰(科进顾问(亚洲)有限公司,香港特别行政区)
Feasibility Study on Power Supply with the Original Power
Supply System Feeding an Extension
Ng Hwa Kit Eric(WSP(Asia)Limited,Hong Kong Special Administrative Region,China)
Abstract: A feasibility study is carried out for utilizing the original power supply system to feed the expansion of a landmark project in Northeast China. The Phase Ⅲ load is estimated. The power consumption of Phase Ⅰ project introduced from the power supply bureau and the actual power consumption of Phase Ⅰ project are analyzed. The power supply distance of utilizing the original power supply system to feed Phase Ⅲ project is analyzed. Finally,conclusions are drawn in this paper:the power supply transformation adopts the method of increasing the load factor of the original power supply facilities;the original power supply system is utilized to feed the expansion project,so as to reduce the initial installation cost of the expansion part.
Key words:power supply transformation;load estimation;transformer installation capacity;load factor;initial installation cost;actual power consumption;high voltage incoming line;power supply distance
摘 要:对东北某地标性项目以原供电系统为扩建部分供电进行可行性研究:对3期负荷进行估算;分析从供电局引入1期的供电量及1期的实际用电量;研究采用原供电系统为3期供电的供电距离。最后得出结论:供电改造采用提高原供电设施负载率的方式,采用原供电系统为扩建部分供电,以降低扩建部分的初装成本。
关键词:供电改造;负荷估算;变压器安装容量;负载率;初装成本;实际用电量;高压进线;供电距离
中图分类号:TU852 文献标识码:A
doi:10.3969 / j. issn.1003 - 8493.2022.04.008